Storebelt East Bridge
HMV’s Project Manager. Developed and managed the
complex Aerial Spinning equipment for Aerial Spinning of 20,000 tons of cables. Advised the
contractors, Coinfra S.p.A and GEC Alsthom, on constructability issues.
Commissioned and supervised the spinning equipment production and operation.
Spinning was completed 46 days in front of the accelerated schedule and set the
world record in Aerial spinning.
Employed by Hordaland Mek. Verkstad.
Employed by Hordaland Mek. Verkstad.
A beautiful bridge. |
The wire reeling plant. 24 DC PLC controlled motors in operation continuously. |
The wire reeling plant on the anchor slab |
The massive 175.000 mt cable gravity anchor slap resting on the sand seabed. |
The spinning wheel passing T1 |
The spinning wheel in the main span. |